Contractors To Pay For Repairs To Beleaguered Maryland Transit Hub

Wednesday, April 10, 2013

Preliminary repair work is underway at Maryland' s Silver Spring Transit Center, but officials still can't say when it will actually open.

The construction and design teams have agreed for now to pay for the necessary repairs to fix the structural problems at the Silver Spring Transit Center that were detailed in a scathing county report.

David Dise, director of general services for Montgomery County, says some repair work is already underway but that the major remediation work won't take place until late summer.

"Foulger Pratt was directed on Friday to begin the replacement of the faulty pour strips on the mid-level of the transit center," Dise says. "Parsons Brinkerhoff, the engineer of record, is beginning the design of the other remediation work that has to be done, the columns, the beams, and the topping slabs on the two levels."

That's just the beginning. Those repairs will take months to complete, so Dise can't say when the facility, already two years behind schedule, will open.

"Much of that will depend upon the final remediation plan being developed by Parsons Brinkerhoff and the subsequent schedule developed by Foulger Pratt after they receive the design," Dise says.

So the county, as of now, will not have to pump any more money into finishing the facility.

"The contractors that have performed the work that is in error must bear the cost of its repair," Dise says.

So it appears the county and the contractors have reached a resolution that will avoid costly, time consuming litigation, at least for the time being. The contractors may fight the county in court after the work is done to recover their expenses.

Read More

Comment

Transportation Nation

Maryland County Approves Millions More for Troubled Transit Center

Wednesday, April 03, 2013

Maryland's Montgomery County Council approved an additional $7 million to pay for construction work already completed at Silver Spring Transit Center, which is already two years behind schedule and about $80 million over budget.

The $7 million approved by county lawmakers has nothing to do with major design and construction problems detailed in a county report released two weeks ago.When it comes to who will pay to repair those problems, county officials say it will likely be determined in litigation with the project’s contractors.

“We will move expeditiously to make sure that we make the necessary repairs and that the taxpayers of Montgomery County will not have to pay for the flaws of the contractor,” says County Executive Ike Leggett, who has threatened to cancel the county’s contract with Foulger Pratt and other contractors and sue to recover any funds paid to fix the transit center’s construction issues, like inadequately thick concrete.

“Whatever we spend we will get back because we are going to pursue to the ultimate degree of the law and the legal process to make sure the county is reimbursed for anything we may have to put out in advance,” says Leggett.

Council President Nancy Navarro echoed Leggett’s vow to go to court, if necessary, to protect taxpayers but left open the possibility the county is also responsible for the mess at the transit center.

“I have not said at any moment that the county could not have some responsibility in this. It is possible,” says Navarro, who says the transit center could open to the public while any litigation proceeds. 

No lawsuits have been filed yet.

Contractor Foulger Pratt has said the county’s design plan was flawed from the start. Company executive Bryant Foulger has said any safety issues concerning concrete and reinforcing steel bars are the county’s responsibility.

 