Streams

Megaloads Travel Through Montana City

Thursday, March 10, 2011 - 05:09 PM

A megaload waits on a snowy road (photo by Jackie Yamanaka)

(Helena, MT – Jackie Yamanaka, YPR) – ConocoPhillips successfully transported its two huge megaloads of refinery equipment through the city of Missoula early this morning.

Hundreds of protesters and onlookers flanked the 15-mile route through a major city street.

Each load is 26 feet high and 29 feet wide. The loads are so big crews had to move traffic signals and utility lines out of the way. As described in an earlier TN story, each load is “heavier than the Statue of Liberty, nearly as long as a football field, wider than the roads that they’re actually traveling on, and three stories high.”

Rich Johnson is a ConocoPhillips spokesman who flew to Missoula from Houston to accompany the loads. He says this is the first time he’s worked on a project this big that’s been the focus of intense media and public scrutiny.

“We had a lot of people out watching,” he says. “I mean there were the protesters. But there were many more people out watching to see this pretty amazing, unique site of these huge coke drums being transported through their city.”

The loads are not without controversy. A few protesters did try to block the loads. But they were removed by police. One person was arrested. Last month, the Montana Legislature was set to consider a bill that would have required separating permitting for megaloads, but it was tabled.

The route this morning through Missoula totaled about 15 miles. Johnson says the transport went smoothly.

“It went very well,” Johnson says. “We were able to safely transport our shipment from Lolo through the city of Missoula and ended up at our designated stopping point well before our required stopping time of 6 am.”

It took about an hour and a half to travel the 15-mile route. The load is destined for the company’s refinery in Billings.

The total miles to be traveled over the road is about 700. The loads were manufactured overseas, arrived via ocean freighter after traveling some 5,300 miles and then were sent by river barge to Lewiston, Idaho

When these two coke drums arrive at the ConocoPhillips refinery in Billings, the crews will return to Idaho for the two remaining vessels, also bound for the Billings refinery. The equipment is to be installed next year.

Montana is awaiting another set of megaloads. That one is for an ExxonMobil project destined for the oil tar sand fields of Alberta, Canada.

*****************

You can read more TN coverage about this issue here and here.

Tags:

News, weather, Radiolab, Brian Lehrer and more.
Get the best of WNYC in your inbox, every morning.

Leave a Comment

Register for your own account so you can vote on comments, save your favorites, and more. Learn more.
Please stay on topic, be civil, and be brief.
Email addresses are never displayed, but they are required to confirm your comments. Names are displayed with all comments. We reserve the right to edit any comments posted on this site. Please read the Comment Guidelines before posting. By leaving a comment, you agree to New York Public Radio's Privacy Policy and Terms Of Use.

Sponsored