VIDEO + PICS: As Grand Central Bustles, A New Station Is Clawed From The Rock Below

Thursday, January 31, 2013 - 08:35 PM

http://youtu.be/ULIx8QVZbKU

(New York, NY - WNYC) Michael Horodniceanu, the NY Metropolitan Transportation Authority's master builder, was sweating as he stood in a cavern blasted from the layers of schist below Grand Central Terminal, which marks its 100th year on Friday. He was considering the question of which, in the end, would be thought of as the bigger job: building the original terminal or the the tunnels that the authority is bringing into a new $8.24 billion station it is constructing beneath the existing one.

"This one," he said. "Because people have been building above ground for a long time. We've been digging for a long time--we have about 6 miles of tunnels just in Manhattan. We've been digging under the most expensive real estate you can find in New York."

What's he and hundreds of sandhogs are creating is a project called East Side Access: 350,000 square feet of track, platforms, escalators and concourses that will, for the first time, connect Long Island Railroad to the East Side of Manhattan. It will double the size of Grand Central Terminal without enlarging its footprint, and it is expected to shave 40 minutes off the commutes of about 160,000 passengers per weekday. Currently, Long Islanders who work on the East Side of Manhattan must travel to Penn Station, on the West Side, and double back.

The project is $2 billion over-budget and its 2019 completion date puts it six years behind schedule--another reason Horodniceanu is sweating.

This is people-intensive work," he said. "We use the best technology but, in the end, it takes people." As he spoke, a worker operated a backhoe that clawed rock from a watery pit. The pit was lit by a high-intensity kleig light, which barely held back the subterranean gloom.

Scene from the massive East Side Access project beneath Grand Central Terminal. (photo by Jim O'Grady)

Every day 750,000 visitors pass through Grand Central Terminal, making it the largest hub for train traffic in the world. Of East Side Access's impact on Grand Central Station, Horodniceanu said, "What we are doing now is we are basically preparing it for the next 100 years. "

On left, Michael Horodniceanu, president of MTA Capital Construction, takes an elevator to an excavation site 160 below Grand Central Terminal. (photo by Jennifer Hsu)

(photo by Jennifer Hsu)

(photo by Jennifer Hsu)

(photo by Jennifer Hsu)

(photo by Jim O'Grady)

(photo by Jim O'Grady)

(photo by Jim O'Grady)

(photo by Jennifer Hsu)

Tags:

News, weather, Radiolab, Brian Lehrer and more.
Get the best of WNYC in your inbox, every morning.

Comments [3]

David

I'm no urban planner, but I'd surmise that 8 new tracks connected to the LIRR will very meaningfully impact the overall volume into GCT, Mathias.

Feb. 07 2013 08:58 PM
Matthias

It will double the size of Grand Central Terminal...

One has to wonder whether excavating two enormous caverns is an efficient use of funds for such a small expansion. Given that the terminal already has 67 tracks (and could probably spare a few), adding eight will not double capacity.

Feb. 01 2013 11:17 AM
Tom Swift

OMG! I had no idea the tunneling was going to be so massive, so large, caverns with such high ceilings. Am
absolutely impressed.

Feb. 01 2013 09:18 AM

Leave a Comment

Register for your own account so you can vote on comments, save your favorites, and more. Learn more.
Please stay on topic, be civil, and be brief.
Email addresses are never displayed, but they are required to confirm your comments. Names are displayed with all comments. We reserve the right to edit any comments posted on this site. Please read the Comment Guidelines before posting. By leaving a comment, you agree to New York Public Radio's Privacy Policy and Terms Of Use.

Sponsored