The EPA and General Electric have struck a new deal for the company to remove PCB's from the upper Hudson River. Environmentalists, though, say they are not happy with it. WNYC's Andrea Bernstein reports.

REPORTER: Three years ago, the epa ordered GE to clean up the hudson. But it took until yesterday to get the company to actually agree to begin the process. Under the terms of the consent decree, GE will remove about ten percent of the PCBs, and then, after a peer review, will decide whether to do the rest.

The EPA says if GE refuses to complete the process, it can go to court. But Rick Shiafo of Scenic Hudson says the agreement will only delay the clean up.

SHIAFO: 68 It's a small step forward, its a baby step and what we need to take in this process are big steps.

REPORTER: Under the EPA's most optimistic estimate, the clean up, costing close to $600 million could be complete by 2013. For WNYC, I'm Andrea Bernstein.

More in:

Leave a Comment

Register for your own account so you can vote on comments, save your favorites, and more. Learn more.
Please stay on topic, be civil, and be brief.
Email addresses are never displayed, but they are required to confirm your comments. Names are displayed with all comments. We reserve the right to edit any comments posted on this site. Please read the Comment Guidelines before posting. By leaving a comment, you agree to New York Public Radio's Privacy Policy and Terms Of Use.







URL

If you enter anything in this field your comment will be treated as spam
Location
* Denotes a required field

WHAT'S ON

Audio Help Schedule

Sponsored

Feeds

Supported by